Govt faces major delays over investment projects

Govt faces major delays over investment projects
Stage 2 of Dunedin Hospital had a reported delay of 120%, as of March. (Image: Supplied)
Jem Traylen
The Government is facing significant cost-escalation pressures and delays in delivering investment projects, according to data it released on Thursday.A June Cabinet paper based on data for the March 2024 quarter said net cost escalations across the portfolio totalled $1.2 billion and more than 50 investments had reported delivery delays of over 20% of the initial delivery timeframe.The Government is also upping the pressure on agencies to provide Treasury with better data on their investment proposals.It has been an apparent bugbear of Treasur...

More Policy

Compass dropped in major school lunch shake-up
Policy

Compass dropped in major school lunch shake-up

Ministry appoints 10 regional suppliers; Compass misses out after bidding for RFP.

Cécile Meier 07 Nov 2025
$200m gas fund may not be enough as Māui closure looms
Policy

$200m gas fund may not be enough as Māui closure looms

The fund has been expanded to cover gas storage.

Ian Llewellyn 06 Nov 2025
Seymour promotes coal, nuclear, and privatisation
Policy

Seymour promotes coal, nuclear, and privatisation

Burning some coal to enable more renewable power "not a bad deal".

Pattrick Smellie 05 Nov 2025
EPA head quits with fast-track changes
Policy

EPA head quits with fast-track changes

The latest fast-track reforms go far beyond supermarket resource consenting.