Transmission Gully may open late on 2016 delays although progress made during winter

Transmission Gully may open late on 2016 delays although progress made during winter
Paul McBeth
By Paul McBeth Dec. 22 (BusinessDesk) -  The joint venture building the $850 million Transmission Gully motorway north of Wellington warned the 2016 earthquake followed by torrential rain may delay the road opening, although it made good time in the typically problematic winter months.  The project is working to an April 2020 deadline to open the 27-kilometre, four-lane highway in a complex construction programme, although in heavily redacted documents released under the Official Information Act, project director Boyd Knights of the CPB H...