Cook Strait cable constraints to remain for another winter

Cook Strait cable constraints to remain for another winter
May 1 (BusinessDesk) - Plans to have the Cook Strait cable fully refurbished with a new connection in time for this winter have been stymied by low inflows into the country's hydro-electricity catchments. Meridian Energy noted the delay in fully commissioning the new connection, known as Pole 3, in its quarterly operational report, and national grid operator Transpower says it will still be able to offer between 350 Megawatts and 450 MW of the pole's 700MW rated capacity through the winter months. However, current hydrological conditions make...