Fletcher was under-insured, convention centre subbies claim

Fletcher was under-insured, convention centre subbies claim
Fletcher is still finishing off the convention centre, which caught fire in 2019.
Victoria Young
The waterproofing subcontractor accused of negligence causing the 2019 fire at SkyCity’s International Convention Centre site is fighting claims made by Fletcher Building, and further alleges Fletcher’s construction unit was under-insured. Justice Rachel Tahana is overseeing a 14-week court action by Fletcher Construction against XAM Limited, formerly known as MPM Waterproofing, as well as XAM’s subcontractor, JEL. In May last year a preliminary judgment in the proceeding put Fletcher’s uninsured losses claim a...

More Property

The key question driving Fletcher's asset sales
Property

The key question driving Fletcher's asset sales

Construction is for sale, and now residential could be too. What's next?

Fletcher Building's loss balloons to $419m
Property

Fletcher Building's loss balloons to $419m

Fletcher boss says 2025 has been one of its most demanding years in recent memory.

Auckland Council proposes downzoning 12,000 properties
Policy

Auckland Council proposes downzoning 12,000 properties

The council is also proposing to enable 10-15 storey apartments around more than 40 hubs.

Oliver Lewis 19 Aug 2025
Grimshaw ruling overturned
Property

Grimshaw ruling overturned

Lower court had found the law firm was negligent. 