UPDATE: Pohokura maintenance to cut production again

UPDATE: Pohokura maintenance to cut production again
Gavin Evans
(Adds detail of rig in transit, planned work programme, from 12th paragraph.) By Gavin Evans Jan. 14 (BusinessDesk) - Production from the offshore Pohokura gas field is to be cut for a third time in a year next month. OMV, which last month became operator of the field from Shell, plans a range of interventions in the field’s offshore wells to optimise their production. The work means that, for safety reasons, production from the five offshore wells will be stopped for about 30 days – 12 days in February and a further 18 days during...