PALM VALLEY-12 WEEKLY DRILLING UPDATE 11th October

GENERAL
Tue, Oct 11 2022 09:27 am

11 October 2022
Palm Valley-12 DRILLING UPDATE

The Operator (“Central”) (ASX: CTP) advises that as at 0600 hrs ACST on 10 October 2022 Palm Valley 12 (PV12) sidetrack (ST2) in OL3 (the Palm Valley Production License) was undergoing clean-up flows in preparation for a further flow test.
The well reached a total depth (“TD”) of 3,039m measured depth (“MD”) on 8th October 2022.

After flow testing is complete, operations will commence to run production tubing and complete the well as a gas producer.
The PV12 ST2 well is being drilled under a joint venture between Central (50% interest), New Zealand Oil & Gas Limited (ASX: NZO) (35% interest) and Cue Energy Resources Limited (ASX: CUE) (15% interest).

Figure 2: Location of Permit OL3 and Palm Valley-12 ST2 appraisal well.


Announcement PDF


Markets News

War on the Nasdaq
Opinion

Simon Robertson: War on the Nasdaq

Who wins as Michael Burry declares war on AI?

Simon Robertson 08 Nov 2025
Markets

NZ sharemarket shakes off Wall Street fall to end firm

New Zealand shares shook off weakness in overseas markets.

Jamie Gray 07 Nov 2025
NZ sharemarket shakes off Wall Street fall to end firm
Markets

Seeka uncovers $350k fraud, sacks employee

Three companies have been identified as being involved in the fraud, CEO says.

John Anthony 07 Nov 2025
Seeka uncovers $350k fraud, sacks employee