Continued strong hydro conditions in FY23 Q4 drove lower carbon emissions and reduced portfolio generation costs. Customer numbers continued to grow, with 3,779 customers gained in the quarter.
Malcolm Johns, Chief Executive said, “Genesis continued to perform well through the final quarter of the year. We know that the current hydro conditions will eventually change but it was pleasing to see that Genesis can respond to market conditions to reduce carbon emissions and generation costs.”
Huntly Unit 5 Outage
Genesis’ Huntly Unit 5 combined cycle gas turbine remains unavailable, following a forced outage on 30 June. An investigation has revealed a failure of one of the unit’s three circuit breakers. Specialist parts, including some from overseas, are required for repair. The unit is currently expected to be returned to service by 31 August 2023.
High hydro storage, alternative plant availability and wholesale electricity market conditions have combined to mitigate the financial impact of the outage to date.
Updates on the return to service of the unit will be provided through the Transpower Planned Outage Coordination Process (POCP).
Genesis’ FY23 Q4 Performance Report is attached.
ENDS
For investor relations enquiries, please contact:
Tim McSweeney
GM Investor Relations & Market Risk
M: 027 200 5548
For media enquiries, please contact:
Chris Mirams
GM Communications & Media
M: 027 246 1221
The S&P/NZX 50 Index closed at 12,904.11, up 149.96 points or 1.18%.
Cost savings were behind the decision to delist, the company says.
Partnership with TA Associates tipped to accelerate Craigs' growth.
To join your company account for BusinessDesk and enjoy full access, enter your email and we’ll send you details