Puhoi to Warkworth PPP claim adds pressure to stretched land transport fund

Puhoi to Warkworth PPP claim adds pressure to stretched land transport fund
Paul McBeth
The New Zealand Transport Agency has provided for an $83 million claim on the unfinished $709.5 million Puhoi to Warkworth road, adding even more pressure to an already stretched budget.The project is the second public-private partnership used by the NZTA and, like Transmission Gully in Wellington, it appears to have run into delays and cost overruns even before the covid-19 pandemic shut down all activity for four weeks.In the NZTA’s December quarter performance report – released publicly this week – the government agenc...

More Policy

EPA tips firm on fast-track list into liquidation
Policy

EPA tips firm on fast-track list into liquidation

Energy Farms changed its name the same day it was liquidated.

Gregor Thompson 13 Jun 2025
Massive shake-up for Auckland planning rules
Policy

Massive shake-up for Auckland planning rules

RMA Reform Minister Chris Bishop pushes council to upzone around the $5.5b CRL.

Oliver Lewis 11 Jun 2025
Robert Walters NZ reviews structure as govt temp cuts bite
Policy

Robert Walters NZ reviews structure as govt temp cuts bite

Revenue collapsed 31% to $202.4m in 2024 after tripling between 2017 and 2023.

Gregor Thompson 09 Jun 2025
EPA applies to liquidate company on fast-track list
Policy

EPA applies to liquidate company on fast-track list

Energy Farms did not pay costs relating to the application process.

Gregor Thompson 06 Jun 2025